Need a Thames-Coromandel building consent? Most building projects in the Coromandel need one before any work starts, and knowing the process saves time and money. Here's how a building consent works at Thames-Coromandel District Council, step by step, from your first application to the code compliance certificate at the end.
Do you need a building consent?
The council says most projects need a building consent before any building work starts, unless the work is exempt. Consent is also often needed for things like pools and fireplaces. Even exempt work must still meet the Building Code. The council's building consent exemptions page explains what's exempt.
The Thames-Coromandel building consent process at a glance
| Step | What happens | Timeframe |
|---|---|---|
| 1. PIM (optional) | A project information memorandum tells you what the council knows about the site and project | Must be issued within 20 working days |
| 2. Prepare and apply | Plans and documents lodged online, and the deposit paid | Council aims to vet applications within 48 hours |
| 3. Processing | The council checks the application against the Building Code | 20 working days, with the clock paused for any requests for information |
| 4. Start work | Work begins once the consent is issued | Must start within 12 months, or the consent lapses |
| 5. Inspections | Council inspectors check the work at set stages | Book with at least 48 hours' notice |
| 6. Code compliance certificate | Final sign-off that the work matches the consent | Issued within 20 working days of a complete application |
Step 1: Get a PIM (optional)
A project information memorandum (PIM) is optional for most projects, but it's a useful early check. The council must issue it within 20 working days of receiving the application. A PIM is required, though, if you're building a small standalone dwelling under the granny flat exemption, which our guide to building a bach explains.
Step 2: Prepare and lodge your application
Most applications at Thames-Coromandel are lodged and processed online, using the council's AlphaOne system, where you can submit, manage and track your application. Before you apply:
- Know the owner's name as it appears on the record of title.
- Prepare a short, accurate description of the project.
- Have your plans and supporting documents ready.
- Pay the deposit. The council's clock starts once it has a complete application and the deposit.
For large or commercial projects, the council offers pre-application meetings, which can reduce requests for further information later.
What does a building consent cost?
Fees depend on the value of the work. From the council's 2026/27 schedule:
| Item | Fee |
|---|---|
| PIM | $436 + online fee |
| PIM for a small standalone dwelling (granny flat) | $1,453 + online fee |
| Residential deposit, work up to $7,500 | $995 + online fee |
| Residential deposit, $7,501 to $20,000 | $2,260 + online fee |
| Residential deposit, $20,001 to $124,999 | $3,175 + online fee + levies as required |
These are deposits, not the final cost. Check the council's full fees schedule for larger projects and other charges.
Step 3: Processing
The Building Act requires the council to process a building consent within 20 working days. If it needs more information, it sends a request for information (RFI), and the clock stops until you've provided everything in full. Complete, clear documents are the best way to avoid delays.
Step 4: Start work within 12 months
Once your consent is issued, building work must start within 12 months, or the consent lapses. You also need to complete the work within two years, but you can apply for an extension before that deadline.
Step 5: Book your inspections
Your consent includes a list of required inspections. You book them by calling the council on 07 868 0425 or emailing building.inspections@tcdc.govt.nz, with at least 48 hours' notice. The council must carry out at least 80% of inspections within 3 working days. A failed inspection means a re-inspection, at extra cost. When everything is finished, you book the final inspection.
Step 6: Apply for your code compliance certificate
When the building work is finished, you or your agent apply online for the code compliance certificate (CCC). Upload all your documents, including the records of work from your Licensed Building Practitioners. The council then has 20 working days to issue the CCC, as long as it's satisfied the work matches the consent. If documents are missing, the clock stops until they arrive. The CCC fee is included in your building consent invoice.
Common questions
How long does a building consent take in Thames-Coromandel?
The council must process it within 20 working days. The clock stops whenever it asks for more information.
How do I apply for a building consent in the Coromandel?
Most applications are lodged online through the council's AlphaOne system.
How long is a building consent valid?
Work must start within 12 months of the consent being issued, or it lapses, and you need to complete the work within two years unless you get an extension.
Want help with your consent?
Paterson Construction is a Cooks Beach building company working across Mercury Bay and the Coromandel. We can work alongside your designer on the documents, book inspections as the build progresses, and help pull together the paperwork for your code compliance certificate. Read our guide to choosing a builder, or talk to Dave about your project.
How we put this guide together: everything comes from Thames-Coromandel District Council's building consent pages and 2026/27 fees schedule, checked in November 2026. Fees and processes change, so check the council's pages before you apply.